Demolition/Site Preparation:

  • Removed existing panelling on the lower portion of walls.
  • Removed existing aluminum wiring and electrical device boxes.
  • Removed existing broadloom.

Drywall and Taping:

  • Installed new drywall on lower portions of walls.
  • Converted existing popcorn ceiling to smooth finish.
  • Enclosed support post at bottom of the staircase with drywall.

Electrical and Lighting:

  • Performed required rough-in wiring for surround sound A/V system.
  • Installed required circuits for standard device boxes, A/V system, and lighting system.
  • Difficult fishing of new electrical lines through the existing structure was required for most of the project.
  • Designed, installed, and commissioned a new lighting system for the whole basement.
  • ESA Certificate of Clearance obtained.

Carpentry Services:

  • Performed framing repairs, as required.
  • Installed new floor mouldings, window trim, and door casements for the entire basement.

Flooring:

  • Arranged for installation of new broadloom for basement and stairway to main floor level.
  • Full, comprehensive cleanup of the work area, and off-site disposal of debris.

The Subtrades we worked with on these jobs:

Electrical
Michael Finlan – Master Electrician
Wireology Inc.
www.wireology.ca

HVAC
Bruce Watson – HVAC Technician
A/C Air Systems Ltd.

Carpet/Broadloom:
Lowes Canada Home Improvement
www.lowes.ca

Drywall Taping and Mudding:
Amil Garcia
A.A.G.H. Drywall and Taping