Ensuite Bathroom:
- Removed existing vanity, shower, toilet, drywall, insulation and aluminum wiring.
- Relocated existing floor HVAC vent to make room for new, larger vanity and sink.
- Installed new shower and basin with associated faucet and shower head.
- Installed new custom ceramic tile shower with prefabricated glass door.
- Installed new custom ceramic floor with radiant heat system.
- Installed new BROAN™ fan with associated 6” insulated ductwork.
- Designed and installed new lighting and electrical works.
- ESA Certificate of Clearance obtained.
- Installed new Rockwool™ insulation, drywall and trimwork.
- Installed new vanity, faucet, and toilet.
- Complete taping, mudding, and painting of room.
- Full cleanup and off-site disposal of debris.
Master Bedroom:
- Removal of existing carpet from site.
- Installation of additional subfloor material to prevent squeaking of new flooring.
- Installation of new broadloom.
- Complete painting of room.
- Full cleanup and off-site disposal of debris.