Ensuite Bathroom:

  • Removed existing vanity, shower, toilet, drywall, insulation and aluminum wiring.
  • Relocated existing floor HVAC vent to make room for new, larger vanity and sink.
  • Installed new shower and basin with associated faucet and shower head.
  • Installed new custom ceramic tile shower with prefabricated glass door.
  • Installed new custom ceramic floor with radiant heat system.
  • Installed new BROAN™ fan with associated 6” insulated ductwork.
  • Designed and installed new lighting and electrical works.
  • ESA Certificate of Clearance obtained.
  • Installed new Rockwool™ insulation, drywall and trimwork.
  • Installed new vanity, faucet, and toilet.
  • Complete taping, mudding, and painting of room.
  • Full cleanup and off-site disposal of debris.

Master Bedroom:

  • Removal of existing carpet from site.
  • Installation of additional subfloor material to prevent squeaking of new flooring.
  • Installation of new broadloom.
  • Complete painting of room.
  • Full cleanup and off-site disposal of debris.